Gravity Sewer installation of 20,795 LF of 48” Fiberglass Pipe, 3,780 LF of 21” PVC Pipe, 2,180 LF of 18” PVC Pipe, 1,820 LF of 15” PVC Pipe, and 1,520 LF of 12” PVC Pipe, 545 LF of 72” CPP Pipe (Storm Sewer), 1,650 LF of 60” CPP Pipe (Storm Sewer). Five (5) crossings by tunnel boring methods totaling 1,308 LF. Three (3) of the crossings totaling 576 LF utilizing a 66” Steel Casing pipe, the remaining two (2) crossing utilizing “Direct Jack” 48” Hobas Fiberglass pipe, by tunnel boring methods.

51428 Grand Island - 02
51428 Grand Island - 01
51428 Grand Island - 03
51428 Grand Island - 04
51428 Grand Island - 05
51428 Grand Island - 02 51428 Grand Island - 01 51428 Grand Island - 03 51428 Grand Island - 04 51428 Grand Island - 05

Project Information

Project Number:

Project Category: Underground Utilities, Tunneling

City / State: Grand Island, NE

Final Contract Amount: $ 21,105,303.59

Start Date: September, 2014

Owner: City of Grand Island-

Engineer: Black & Veatch