Gravity Sewer installation of 3,886 LF of 48” Fiberglass pipe, 2,590 LF of
42” Fiberglass pipe, 1,540 LF of 36” Fiberglass pipe. 8,180 LF of 36” Pre-stressed Concrete Cylinder Pipe (PCCP). 3,445 LF of 36” High Density Polyethylene (HDPE) pipe by Horizontal Directional Drill.

51410 Harford - 01
51410 Harford - 03
51410 Harford - 02
51410 Harford - 01 51410 Harford - 03 51410 Harford - 02

Project Information

Project Number:

Project Category: Underground Utilities, HDD

City / State: Harford County, MD

Final Contract Amount: $ 16,407,978.95

Start Date: June, 2014

Owner: Harford County - Department of Procurement

Engineer: Arcadis U.S., Inc.